Where can you find the grounding and bonding requirements for FMC?

Prepare for the CSAP Level 2 Exam with our comprehensive quiz. Practice with varied question types, including flashcards and multiple-choice, all with helpful hints and detailed explanations. Build your confidence and optimize your study time for exam success!

The grounding and bonding requirements for Flexible Metal Conduit (FMC) are specifically outlined in Sections 348.60 of the National Electrical Code (NEC). This section provides detailed guidelines on the proper installation practices, ensuring that the FMC systems are effectively grounded and bonded to enhance electrical safety and reduce the risk of fire or electric shock.

The focus of grounding and bonding in this context is vital, as it serves to protect both the electrical system and the users from potential hazards. Understanding these requirements is crucial for compliance with safety standards and for the overall integrity of electrical installations using FMC.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy